PERT Chart Example
1- Calculate the contents of the nodes in the above PERT Chart.
2- Assuming the task lengths are in days, how many days will it take to complete the project?
22 Days
3- Which tasks are on the critical path?
A-B-C-E-I
4- The person working on task G tells the project manager he can’t start work until one day after the scheduled starting date. What impact would this have on the completion time of the project?
no impact , G isn’t on Critical Part
5- The project manager decides to reduce the time needed for tasks D and F by one day each. How effective will this reduction be in achieving her aim of maintaining the original finish time for the project?
No effect.Because task D and F are not on the critical path.